• +44-190-022-0819 +44-190-022-0819
  • +1-248-268-9041 +1-248-268-9041
  • +61288800241 +61288800241

SEARCH SOLUTION

Search your solution from list of 1000+ questions

22-08-2018

Product Code: Project-Management-AW366

PROJECT MANAGEMENT

In addition to the recently completed headquarters for the firm, the managerial team for rapidly growing TBE Inc.has decided to build a second building to house the firm’s ever increasing staff.  To complete the building so that the management staff could be in their new offices relatively soon, William Stort, the VP of Facilities who had overall responsibility for the project’s completion, decided to apply some project management techniques.  This required that he research all the various activities that were required as part of this project and understand how they were related.  Assume that today’s date is February 1st, 2015.

 

Note: Prepare your submission assuming that you are the project leader and that you are providing this information to the project manager and project team at a project “kick-off” meeting.  Thus, a professional appearance and clear and concise responses (explaining your answers and showing relevant calculations) are required.

 

  1. Completed Activity Table

Activity Table (template attached) with “Immediate Predecessors” and “Crash Cost per Week” columns completed. It is expected that each person in your group complete this step individually prior to meeting together to discuss differences.

 

 

  1. Work Breakdown Structure

Prepare a Work Breakdown Structure for the construction of the administrative building. You should use all of the tasks the case has described as well as adding at least 10 of your own. It is NOT expected that the WBS be in MS Project, a Microsoft Word document is sufficient. The WBS should not exceed 1 page. Use either an indented or tree format.  The additional tasks are for this question only.

 

  1. Path Identification

Identify the paths and the length (in weeks) of each path.  Specifically identify the critical path(s).

 

 

  1. Project Duration & Cost

What are the project duration and overall cost in which the building can be occupied by management staff under normal times and costs?

 

  1. Project Crashing

William is considering completing this project in the shortest time possible.  What is the fastest the project can be completed, and the associated costs of that approach (without incurring any unnecessary costs)? Your solution must indicate the step by step(one week at a time) order and duration of the ‘crashing’ of activities so that the board can choose their preferred combination of cost and schedule.

 

  1. Complete project by January 1st? For public “optics” of project progress, the board of directors was interested in having the project complete by January 1st, 2016.  Would this be possible?  If so, how much would the project cost?

 

  1. Activity Delay

After receiving approval from the board in the normal time, William ran into problems obtaining the necessary building permits.  The land on which the building is planned to be built on was recently zoned as residential.  As a result, a re-zoning approval had to accompany the building permits.  This re-zoning approval required an additional two weeks to obtain.  If William wants to complete the project in the original “normal” time determined in Question #5, what specific actions must he know take to minimize costs while still completing the building as originally scheduled?

 

  1. Project Triangle

Recognizing that the company is growing at a rapid rate and may need the additional space offered by the new building sooner than they expect, the board of directors is considering providing additional funding for the project.  The board would like to know how a potential “budget increase” of a few hundred thousand dollars could impact the other aspects of the project. Assume the project has recently begun and is progressing at the normal schedule pace.

 

 

 

 

 

 

 

 

Download Questions

Product Code: Project-Management-AW366

Related Questions in (Project Management)

13-01-2018

Solution: The Journal of Helene Berr and Rue Ordener, Rue Labat 2 evidences that prove the difficulty and destructiveness that the people had to face in those four years. As mentioned by Berr (2009, p.23), in h ...

18-01-2018

Solution: Employee communication highlights the sharing of ideas and information. In this competitive business world, information exchange is essential among employees to develop team performance effectively. m ...

18-01-2018

Solution: As per Section 1 of the Thirteenth year plan describes about China’s two key objectives that will be accomplished if the National People’s Congress or the standing committee of this party passes t ...

18-01-2018

Solution: (Feldman 2005) reference information extraction to be one of the weightiest pre-processing method that escalates the text mining potential significantly. Pre-processing is an essential part in informa ...

18-01-2018

Solution: The pro forma income statement represents a trending statement that includes the probable net income value for the company considering the current growth and decline rates valid throughout the period ...

18-01-2018

Solution: Mode is defined as the value which occurs more frequently in the data set. The mode for non-business is 82 while for business is only 59. P value can be calculated from z table . As per z table p valu ...

18-01-2018

Solution: ABC assumes that there are different activities involved in different processes that cause costs andthe product, services, and customers are reasons for those activities. The UK customer segment is br ...

19-01-2018

Solution: Residual earnings valuation method is used to calculate the intrinsic value of the stock based on the expected residual income of the company in the coming years. The residual income is discounted bac ...